Behind-the-Meter Power for Data Centers: Project Table

Behind-the-meter power is generation on the customer's side of the utility meter, so it serves the site directly instead of arriving through the grid (National Renewable Energy Laboratory). Some data center developers now plan it, or generation built next to the site, instead of or alongside a grid connection. The table lists 24 publicly announced projects, each sourced to a filing or the company's own announcement.

Megawatt Index Editorial Team

Updated October 16, 2026Dataset24 projects

Showing 24 of 24

Announced on-site and behind-the-meter power projects for data centers
Project MatadorTexas11,000AnnouncedSourcechecked 2026-10-16
GW RanchTexas7,650PermittedSourcechecked 2026-10-16
Homer City Energy CampusPennsylvania4,400Under constructionSourcechecked 2026-10-16
Talen and Amazon expanded Susquehanna power purchase agreementPennsylvania1,920AnnouncedSourcechecked 2026-10-16
Oklo and Meta power campus in Pike CountyOhio1,200AnnouncedSourcechecked 2026-10-16
AWS data center campus adjacent to Susquehanna (sale and co-located supply)Pennsylvania960RestructuredSourcechecked 2026-10-16
Crusoe 900 MW AI factory campus in Abilene for MicrosoftTexas900AnnouncedSourcechecked 2026-10-16
Google data center campus in Armstrong County developed by CrusoeTexas531Under constructionSourcechecked 2026-10-16
Susquehanna amended interconnection service agreement (co-located load increase)Pennsylvania480CancelledSourcechecked 2026-10-16
Apollo Power Generation FacilityOhio350PermittedSourcechecked 2026-10-16
Cascade Advanced Energy FacilityWashington320AnnouncedSourcechecked 2026-10-16
Small modular reactor near North Anna nuclear stationVirginia300AnnouncedSourcechecked 2026-10-16
Socrates the Younger (STY) Power Generation FacilityOhio250PermittedSourcechecked 2026-10-16
Socrates South Power Generation ProjectOhio200PermittedSourcechecked 2026-10-16
Socrates North Power Generation FacilityOhio200AnnouncedSourcechecked 2026-10-16
PowerConneX 1 Generation ProjectOhio120PermittedSourcechecked 2026-10-16
Bloom Energy fuel cells at Equinix IBX data centersMultiple or not stated100OperatingSourcechecked 2026-10-16
Redwood Energy and Crusoe modular data center microgridMultiple or not stated12OperatingSourcechecked 2026-10-16
AEP Ohio onsite fuel cells for AWS and Cologix data centersOhioPermittedSourcechecked 2026-10-16
Bloom Energy fuel cells for CoreWeave at Chirisa Technology Parks data centerIllinoisAnnouncedSourcechecked 2026-10-16
Bloom Energy fuel cell expansion at Intel's Santa Clara high-performance computing data centerCaliforniaAnnouncedSourcechecked 2026-10-16
Crusoe AI data center at the Lancium Clean CampusTexasUnder constructionSourcechecked 2026-10-16
Joule energy and data center campusUtahAnnouncedSourcechecked 2026-10-16
xAI Colossus data center natural gas turbinesTennesseePermittedSourcechecked 2026-10-16
Coverage
U.S. projects that give a data center on-site, co-located or bridge power: gas turbines and engines, fuel cells, co-located nuclear, small modular reactor agreements and solar plus storage. Announced through October 2026.
Sources
SEC filings, Ohio Power Siting Board
Last updated
, 24 projects

How this was built

Each row is one announced project or one status change to a project, sourced to an SEC filing, a state regulator filing or the developer's own press release. Capacity is the figure in that source, as announced. The configuration column records what the source says: fully behind the meter, co-located but grid connected, or bridge power until a grid connection is ready.

For the utility rules that apply when a large site connects to the grid instead, see the large-load tariff tracker.

Limits of this data

  • Capacities are as announced. Many projects are proposals; an announcement or a permit does not mean the plant will be built at that size.
  • The list is not complete. It covers projects we could source to a primary document; some announced projects could not be confirmed and are left out.
  • One row cites a news report because no primary document could be opened; the source column shows which.
  • Federal Energy Regulatory Commission orders could not be opened directly, so FERC decisions appear only where a company filing reports them (the Susquehanna decision is carried through Talen Energy's annual report).

Sources

  1. 1.NREL, definition of behind-the-meter
  2. 2.SEC EDGAR full-text search

Frequently asked questions

What does behind the meter mean for a data center?

The generator sits on the data center's side of the utility meter and powers the site directly. Power used this way does not flow through the utility's grid to reach the site, although many sites keep a grid connection as well.